WEEK-LONG 24/7 LANE CLOSURES ON LOWER WORLD WAY AT TERMINAL 2 TO SUPPORT AUTOMATED PEOPLE MOVER PEDESTRIAN BRIDGE FOUNDATION CONSTRUCTION

 

Activity:

Beginning Saturday, Sept. 19, 2020 at 11:00 p.m., one week of 24/7 lane closures will be in place on Lower World Way at Terminal 2 to support the drilling of a pedestrian bridge Cast-in-Drilled-Hole (CIDH) foundation for the Automated People Mover train system. Through traffic will still be maintained on Lower World Way, but travelers should allow extra time to access the terminals. This closure will also impact the Lower World Way entrance to Parking Structure 2B, which will only be accessible from Upper World Way.

 

Dates:

Saturday, Sept. 19, 2020 at 11:00 p.m. to Friday, Sept. 25, 2020 at 5:00 a.m.

 

 

*Dates and times subject to change.



Map 1

Week Long Closure

 

Map 2

APM Foundation Lane Closure

 