* WORK RESCHEDULED TO THURSDAY *
INTERMITTENT LANE CLOSURES
NEAR AIRPORT POLICE FACILITY
Activity:
Crews will start micro-tunneling activities inside the Airport Police Facility site and continue underground, heading south under Westchester Parkway to Northside Parkway. All work is underground and no above-ground trenching is required for this activity. The rolling lane closures will allow a crew member to conduct an above-ground survey of the tunneling activities across the intersection.
Date:
Thursday, July 30, 2020 (rescheduled from Wednesday, July 29)
TIME
7 a.m. – 5 p.m.
Construction schedules are subject to change.
IMPACTS:
During work hours, the rolling closures will affect only one lane at a time on Westchester Parkway. The east-side pedestrian crosswalk may also be closed temporarily.
CONTACT:
Charles H. Pannunzio, Los Angeles World Airports Public Relations Division,
(424) 646-5260