Please disregard the previous version of Advisory 2024-05 and use this Revision 1 version that removes the previously outlined Taxiway E and Taxiway R ADG V and smaller restrictions. That restriction has been cancelled.
Runway 6R-24L will be closed for 132 consecutive calendar days (estimated) beginning March 06, 2024 (0030L/0830Z) through July 18, 2024, for Phase 4 of the North Airfield Exit Taxiways (NAET) Project.TheNAET Project will construct four new exit taxiways south of Runway 6L-24R that will connect to Taxiways D and E by the end of the project.
Taxiways R, AA, and BB will remain available for aircraft access to and from Runway 6L-24R during this Phase 4 construction, with the exception of occasional nightly closures that are required at the beginning and end of this phase to enable the long term closure and eventual reopening of Runway 6R-24L.
Please review the below items for more information.