Taxiway C Closure Between Taxilane C9 and Gate 59

06/01/2022 12:00 PM

Advisory: 2022-08
June 1, 2022
Taxiway C Closure
Between Taxilane C9 and Gate 59
Taxiway C will be closed between Taxilane C9 and Gate 59 from June 14, 2022 until July 25, 2022. This closure is to support the Taxiway C pavement reconstruction project and will include demolition of the current asphalt pavement, construction of new concrete pavement, and installation of taxiway markings, signs and lighting.
 
Please expect the FAA Air Traffic Control Tower to provide alternate routing instructions around this taxiway closure for taxiing or towing aircraft.
 
Drivers should use caution when driving around the construction area due to high traffic and temporary changes that may occur. Vehicle Service Road (VSR) C and the crossings between VSR C and Terminal 5, between VSR C and Terminal 4, and between Terminal 4 and Terminal 5 will remain available. However, vehicles will not be able to drive around the southwest corner of Terminal 5 due to construction.
 
Drivers should also be alert and use caution when driving northbound and southbound along the east side of Terminal 4 in Taxilane C9 for aircraft pushing back from Gates 42A and 51B as the aircraft wingtips will need to encroach into closed gate 46B so that the aircraft can be turned around to get the aircraft positioned tail north at ramp control spot #2.
Closures
Duration
C between C9 and Gate 59
6/14/2022 (02:00L) - 7/25/2022 (23:59L)
C9 between B and C
6/13/2022 (00:30L) - 7/25/2022 (23:59L)
Gate 57
6/13/2022 (12:30L) - 7/25/2022 (23:59L)
Once this closure concludes on July 25, 2022, a new closure of Taxiway C between Taxilane C10 and Taxilane C9 can be expected shortly after, which will last an estimated 85 days. A separate LAX Operations Advisory will be issued with additional details closer to the start date.
Temporary Pushback Procedures

Gate 59 -Aircraft pushing back from Gate 59 will need to coordinate with the FAA Air Traffic Control Tower for pushback instructions. Aircraft will need to be pushed tail-east, abeam Terminal 6, prior to disconnect and engine start.
 
Gate 51B- Aircraft pushing back from Gate 51B will need to coordinate with the American Airlines Ramp Tower for pushback instructions. Aircraft will need to be pushed tail south in the C9 Taxilane and then spin in the taxilane, abeam closed Gate 46B, so that the aircraft will be tail-north. The aircraft shall stop on ramp control spot #2.
 
Gate 42A-Aircraft pushing back from Gate 42A will need to coordinate with the American Airlines Ramp Tower for pushback instructions. Aircraft will need to be pushed tail south in the C9 Taxilane and then spin in the taxilane, abeam closed Gate 46B, so that the aircraft will be tail north. The aircraft shall stop on ramp control spot #2.
Click to download work plan
Notices to Air Missions (NOTAMs) will be issued 72 hours prior to the closure. Please plan flight operations accordingly and check current NOTAMs athttps://notams.aim.faa.gov/notamSearchfor current airfield operating conditions.
For questions or comments regarding this advisory, please contact the Airside Construction Office atLAXAirfieldConstruction@lawa.org. For any immediate hazards/questions, please contact the ARCC at(424) 646-LAWA (5292).