Work continues on the Automated People Mover guideway superstructure as it approaches the future Consolidated Rent-A-Car facility.
Column construction is complete for the Automated People Mover guideway segment that will service the system's Maintenance and Storage facility.
Crews work to install guidebeams and pivot switches for the test tracks servicing the Automated People Mover system's future Maintenance and Storage facility.
Following the completion of work constructing the guideway superstructure, work can begin on the Automated People Mover system's concrete tracks.
Once construction of the Automated People Mover guideway superstructure to the north and south of Century Boulevard is complete, crews will span the roadway using a cast-in-place technique that utilizes a traveling form instead of falsework.
Advancement of guideway and parking structure construction at the future West Central Terminal Area station hints at the transformation to come.
Crews prepare for concrete placement for the new parking structure located at the future West Central Terminal Area station.
The APM guideway will curve around the Los Angeles International Airport Theme Building and pass by the LAX Control tower as it approaches the future Center Central Terminal Area station.
At the future Center Central Terminal Area station, construction of the upper columns that will support the station's platform level is nearly complete.
The Automated People Mover train maintenance canopy freshly painted.
A view of the southside of the Intermodal Transportation Facility-West.
A view of the future Security and Badging Office lobby at the Intermodal Transportation Facility-West.
The Los Angeles Department of Water & Power electrical yard at the Intermodal Transportation Facility-West, which was fully energized on March 17.
Escalator canopy construction continues at the Intermodal Transportation Facility-West.
Interior painting for wayfinding and parking spot delineation continues at the Intermodal Transportation Facility-West.
Construction has started for the Automated People Mover station at the Intermodal Transportation Facility-West.
Paver installation on the ground floor of the Intermodal Transportation Facility-West.
The northside of the Intermodal Transportation Facility-West.
Steel erection for the Automated People Mover station canopy at the Consolidated Rent-A-Car facility.
Northwest corner of the Consolidated Rent-A-Car facility Ready Return building.
Carpenters installing column capitals, beams, and tables on the second level of the Consolidated Rent-A-Car facility Idle Storage building.
Consolidated Rent-A-Car facility Idle Storage building second level suspended slab deck pour.
Placement of slab rebar and preparation for a first to second level ramp concrete pour at the Idle Storage building of the Consolidated Rent-A-Car facility.
The Quick Turn Around building Reclaim Water Tanks at the Consolidated Rent-A-Car facility.
Workers installing a car lift in a maintenance bay of the Quick Turn Around (QTA) at the Consolidated Rent-A-Car (ConRAC) facility.
Future car wash bays in the Quick Turn Around building at the Consolidated Rent-A-Car facility.
“Topping off” pour of the last suspended slab at the Consolidated Rent-A-Car facility Quick Turn Around building.